Retaining Wall Block Calculator: Blocks, Caps and Drainage Rock

Count blocks and caps from the courses you will actually stack, then the leveling pad and the drainage rock behind the face. This is a material takeoff. It does not design the wall.

Wall

Along the face. Feet, or feet and inches.

Height you see above grade, not including burial.

A common manufacturer minimum is the greater of 6 inches and 1 inch per 8 inches of exposed height. That is guidance from the block, not a permit rule.

Face length. 18 inches is a common modular block.

Face height. 8 inches gives six courses for 3 ft exposed plus 6 in burial.

Sensible default: 5%. Applied after whole courses and whole blocks per course are counted.

Along the wall. Waste is applied before the cap count is rounded up.

Leveling pad

18 inches is a common trench width.

6 inches compacted is a common start.

1.40 loose tons per cubic yard.

This example uses 20% so the tons match a known check. A usual crushed-base starting point is 25%.

Drainage rock

12 inches of open drainage rock behind the face is a common detail.

1.35 is the open-graded starting point. No compaction allowance is added.

Leave at 0 unless the manufacturer publishes a core volume. The behind-wall tonnage does not include cores until you enter one.

Added once per outlet. Outlets are counted about every 50 feet of wall when the drain is on. Use 0 if you only want the length of the wall.

Added to wall height plus the drainage zone for a fabric area.

Order this

Working…

Blocks and caps

Courses, including burial
—
Blocks per course
—
Blocks before the last round
—
Blocks to order
—
Caps before rounding
—
Caps to order
—

Leveling pad

In place
—
Loose volume
—
Exact tons
—
Order
—

Drainage rock behind the wall

Volume
—
Tons
—
Filter fabric
—

With these numbers

Units and assumptions

Input units
Length and exposed height in feet. Burial, block face, caps, pad, and drainage zone in inches. Metric mode uses meters and centimeters. Weight is US short tons.
Density default
Leveling pad 1.40 loose tons per cubic yard. Drainage rock 1.35. Basis: published loose figures for crushed base and open drainage stone. An 18 by 8 inch face is a common modular block.
Compaction
The pad is compacted. This example uses 20% extra loose volume. A usual crushed-base start is 25%. Drainage rock is open-graded and gets no compaction allowance.
Waste
Sensible default 5%, applied after whole courses are counted and before the final block and cap round-up.
Rounding
Courses and blocks per course round up first. The block and cap orders then round up to a whole unit. Pad tons round up to the next 0.5 ton.
Supplier check
Results are estimates. Confirm quantities with your supplier. This page does not design the wall or decide a permit.

The formula

Courses = round up( (exposed height + burial) ÷ block height ). Blocks per course = round up( length ÷ block length ). Both of those round up first, because you cannot set a fraction of a block in a course. Blocks to order = round up( courses × blocks per course × (1 + waste) ).

Caps = round up( length ÷ cap length × (1 + waste) ). Waste is inside the round-up. Rounding the caps first and then adding waste counts a different number.

Pad volume = length × width × depth ÷ 27, then × (1 + compaction allowance) for the loose cubic yards, then × loose density for tons. Drainage rock behind the wall = length × (exposed + burial) × zone depth ÷ 27, with no compaction allowance. Core fill is added only when you enter a cubic-foot volume per block. Geogrid is not calculated.

Worked example

A 40 foot wall, 3 feet exposed, 6 inches of burial, 18 by 8 inch face block, 18 inch caps, 5% waste. The pad is 18 inches wide and 6 inches deep, compacted, at 1.40 tons per cubic yard and 20% extra loose volume. Drainage rock is 12 inches behind the wall at 1.35 tons per cubic yard, with no core fill entered.

Starting points

Block face, cap length, pad size, and the drainage zone all come from the product and the detail, not from a universal wall. An 18 by 8 inch face is a common modular block, about one block per square foot of face before the course rounding. Some systems run nearer 1.5 units per square foot. Enter that unit’s real face size. Burial below the greater of 6 inches and 1 inch per 8 inches of exposed height gets an information note. That note is manufacturer guidance, not a permit limit.

Permit and engineering requirements for retaining walls vary by jurisdiction, wall height, soil, slopes, and loads above the wall. Verify with your local building department. This page provides material quantities only.

Geogrid length and spacing come from the engineer or the manufacturer. This page does not size geogrid.

A perforated toe drain is a common manufacturer suggestion once the exposed wall is above about 4 feet. It is not a permit threshold. Turn the drain on if your detail includes one.

PieceStarting pointIn the example
Block face18 in long × 8 in high6 courses, 27 blocks per course
Cap18 in28 caps after 5% waste
BurialGreater of 6 in and height/86 in on a 3 ft wall
Leveling pad18 in wide × 6 in compacted20% allowance in the example; 25% is the usual base start
Drainage zone12 in behind the faceOpen rock, no compaction factor
Waste5%After whole courses are counted

Questions

How many blocks for a 40 foot wall 3 feet tall?

With 6 inches of burial and an 8 inch block, that wall is 6 courses. At 18 inches long, each course is 27 blocks. Times 5% waste, order 171 blocks.

How many caps do I need?

Forty feet of 18 inch caps is 26.67 caps. With 5% waste that is 28 even, so the order is 28 caps. Waste is applied before the round-up.

How much drainage rock goes behind a wall?

For this 40 foot wall, 3.5 feet tall including burial and 12 inches of rock behind the face, the volume is 5.19 cubic yards, about 7.00 tons at 1.35. Add core fill only if the block manufacturer publishes it.

Does this tell me if I need a permit?

No. Permit and engineering rules depend on the jurisdiction, the height, the soil, and what sits above the wall. The notice on this page does not use a universal height limit. Confirm the project with your building department. The quantities are materials only.